The Land Entitlement Process in Arizona

Entitlement is the chain of approvals that lets raw land be built on. In Arizona it can include a plan amendment, a rezoning, plats and site plans, each with its own hearing and risk.

Published October 23, 2026

The land entitlement process is the series of government approvals that turns raw land into land you can build on. In Arizona that usually means checking zoning and the general plan, amending one or both if they do not fit the plan for the site, then winning plat, site plan and water approvals before permits are issued. Each step is a separate decision with its own hearing, notice rules and appeal risk.

What "entitled" means

Entitlement is a sequence, not a single approval. The steps below run in order for most projects, though some can be skipped when the existing plan and zoning already fit.

Land is entitled when the approvals needed for the intended use are in hand. Raw land may be zoned for ranch use or open space. A buyer who wants homes, retail or industrial space needs approvals that say so. Until then the parcel is worth what its current rights are worth, and a buyer is paying for a chance at more.

Step 1: Due diligence on rights and constraints

Before any application, confirm what the land can do today. Check:

Our raw land due diligence checklist covers the full list. Diligence tells you which approvals you need and which could stop the project.

Step 2: General plan amendment, if the plan does not fit

An Arizona city or town adopts a general plan under A.R.S. 9-461.05. The plan must have a land use element showing the distribution and extent of land uses and standards for density and building intensity, plus a circulation element. Zoning has to follow it: under A.R.S. 9-462.01, a rezoning ordinance must be consistent with and conform to the general plan.

If your proposed use is outside the plan, the plan changes first. Under A.R.S. 9-461.06:

The statute leaves the criteria for "major" to each plan, so ask the city early. Cities also run their own neighborhood meeting and hearing rules.

Step 3: Rezoning

Zoning sets the actual development standards. The request goes through staff review, a planning and zoning commission hearing, and a vote by the council or board of supervisors. Our guide to how to rezone property in Arizona walks through the application, citizen participation and hearing steps.

For cities and towns, A.R.S. 9-462.04 requires published notice at least 15 days before the hearing and a written commission recommendation. If owners of 20 percent or more of the property in the zoning area (the parcel plus everything within 150 feet) protest in writing, the change needs a three-fourths vote of the full governing body. The change takes effect no sooner than 30 days after final approval.

Maricopa County's published chart shows about six months from application to the Board of Supervisors hearing, assuming two review cycles. We have not found a statewide figure, and cities vary.

Rezonings often come with conditions. Under A.R.S. 9-462.01 a municipality can tie a change of zone to a development schedule. If development does not happen by the deadline, the body can extend the schedule or revert the zoning after a hearing. It can also require dedication of rights-of-way, drainage and utility land if reasonably needed because of the rezoning.

Step 4: Development agreement, where used

On larger projects a city may sign a development agreement under A.R.S. 9-500.05. It can cover duration, permitted uses, density, building height, land dedication, phasing, public infrastructure and its financing, and annexation. It must be consistent with the municipality's general or specific plan, it takes effect no sooner than 30 days after final approval, and it must be recorded with the county recorder within ten days. Its burdens and benefits bind successors, so it travels with the land.

Step 5: Plats and site plans

If the project divides the land into lots, the preliminary plat comes first, then engineering plans, then the final plat. A.R.S. 9-463.01 makes an approved preliminary plat a condition precedent to the final plat, and it requires bonds or other suitable security for improvements not yet built. See preliminary plat vs. final plat and our subdivision guide.

A site plan shows how a specific project lays out on the land. Maricopa County's zone change checklist shows how much a site plan holds: access points, dimensions of buildings, parking, utilities and easements, screening, retention areas and lighting. Detail depends on the jurisdiction, so ask the planning office what it requires.

Step 6: Water, ADRE and permits

For six or more lots, state law adds a gate. A subdivider cannot sell lots until the Arizona Department of Real Estate issues a public report, and water documents are part of that application. Our overview of assured water supply in Arizona explains the water side.

After a Maricopa County zone change takes effect, the owner may apply for a zoning clearance and building permit, as long as the property complies with the zoning ordinance. Building permits are the last step of entitlement and the first step of construction.

What adds risk and time

Where this fits in development

Entitlement is the middle of a long chain. Engineering, infrastructure and lot sales follow it. See the land development process step by step and our page on land entitlement in Arizona. Rules change, and the county or city planning office and an Arizona attorney have the final word.

Selling land that needs this work

Entitlement takes time, money and public hearings that most landowners would rather not carry. Red Dirt Property buys land as-is across all 15 Arizona counties, underwrites parcels against its own statewide parcel data, and handles entitlement after closing. There is no agent commission on our purchases. If your land needs approvals before it reaches its best use, start a conversation here.

Questions

Straight answers.

What is land entitlement?

Entitlement means holding the government approvals needed for a specific use: the right zoning and general plan designation, then plats or site plans, water proof and permits. Land without them is valued on its current rights.

How long does the entitlement process take in Arizona?

No statewide figure exists. Maricopa County's own chart shows about six months from zone change application to the Board of Supervisors hearing, assuming two review cycles. A plan amendment, plats and permits add time on top.

When do I need a general plan amendment?

When the use or density you want is outside the general plan's land use element. Under A.R.S. 9-462.01 a rezoning must conform to the plan, and under A.R.S. 9-461.06 a major amendment needs at least two-thirds of the governing body.

What can stop an entitlement?

Common blockers include a neighbor protest that raises the vote to three-fourths (A.R.S. 9-462.04), referendum on plan amendments, missing water documents, and development schedules that can revert zoning if the land is not built on time.